Procuring Clean Energy

Building new generation facilities to support the clean energy transition.

PGE filed with the Oregon Public Utility Commission its final shortlist of recommended projects submitted in response to its 2023 All-Source Request for Proposal – an important step in helping us acquire new clean energy resources and decarbonize Oregon’s power supply. The right mix of energy resources in the right locations can lower energy costs for our communities and ensure reliable power for customers.

Projects on the final shortlist include renewable energy and capacity resources that offer the best value to customers, including solar, lithium-ion battery storage, and hybrid (solar + storage) projects, located within the state of Oregon. The selections demonstrate a commitment to serving customers reliable, clean power, while working to keep customer prices as low as possible.

Read more: Portland General Electric files final shortlist from Request for Proposal to facilitate reliable, affordable power supply during clean energy transition

What kinds of energy resources will Oregon need?

To achieve our 2030 emissions reduction target while maintaining reliability, PGE plans to add a significant amount of clean energy resources to our portfolio. Learn more

Brett Greene, Senior Director of Resource Acquisition, shares the types of resources PGE is pursuing and the role they play in our 2023 Clean Energy & Integrated Resource Plan.

Documents

Included below are PGE’s final documents for the 2023 All-Source RFP issued February 2, 2024.

2023 All-Source RFP Main Document

Included below are redlines of the final issued term sheets and form contracts:

Calendar

In partnership with OPUC Staff and Stakeholders, PGE has developed the following schedule.  The RFP schedule is designed to make timely progress toward PGE’s capacity needs and HB 2021 compliance requirements and is subject to change based on regulatory timing. PGE will update the schedule to reflect any timing changes.

  • February 2, 2024 - PGE issues Final RFP.

  • February 13, 2024 - Post-issuance bidder conference.

    • Content: PGE RFP Team will provide an overview of the bidding requirements, evaluation timeline and bid submission process.

    • When: 1 p.m. - 3 p.m. PST

    • Video recording

    • Slides

  • February 16, 2024 – Notice of Intent to Bid due.

  • February 23, 2024 – Benchmark bids due.

  • April 5, 2024 — Third-Party Solar BTA/APA bids due.

  • April 30, 2024 — All remaining bids due.

  • June 10, 2024 - Initial shortlist identified.

  • June 24, 2024 - Best and final price update.

  • September 17, 2024 - PGE submits request for acknowledgement of FSL.*

  • Q4 2024/Q1 2025 – Final contracts executed with winning Bidders as applicable.*

*These dates are subject to change depending on the quantity and complexity of bids received and should circumstances require.


Dates subject to change.
Rev. 8/29/2024